How do I answer this question? Can you provide the steps also.

Product backlog has got 400 story points worth work.
Baseline velocity is 25 story points.
Total budget to complete this whole work is 200,000.
At the end of second iteration, actual cost = 22,500 and story points completed = 60.
What is the SPI value?
Mark one answer:

A. 1.2
B. 1.1
C. 1
D. 0.83

  • A Team members assign estimates by averaging Planning Poker cards.

  • B The most senior team member prepare the estimates.

  • C Two or three senior team members estimate and take the average of their times.

  • D The team work together to agree on estimates in a group setting.

Files

File Name
Views
Size
Downloads

532

165.4 KB

348

Purchase Individually

  • PMI-ACP

    Premium File

    145 Questions & Answers
    $21.41
    $14.99
  • PMI-ACP

    Training Course

    68 Lectures
    $14.27
    $9.99
  • PMI-ACP

    Study Guide

    587 Pages
    $14.27
    $9.99
×